MALAKWA BRIDGE AND FOUR-LANING PROJECT

Project Name: Malakwa Bridge and Four-laning Project

Project Location: Malakwa, BC

Client: Ministry of Transportation and Infrastructure

Duration: Summer 2014 to Summer 2016

...

Hamilton Transit Center

Project Name: Hamilton Transit Center

Project Location: Richmond, BC

Client: Translink

Duration: 1 year

Value: 11 million

Scope: Demolition, soil remediation, preload, underground utilities,...

Luxor Bridge

Project Location: North of Radium Hot Springs

Client: Ministry of Transportation and infrastructure

Duration: 6 month

Value: 3.9 Million

Scope: Construct a...

CARIBOO OVERPASS

Project Name: Cariboo overpass

Project Location: Burnaby, BC

Client: Transportation Investment Corp

Duration: 1 year

Value: 9 million

Scope: Excavation and...

North Road Widening

Tybo contracting was selected by the Ministry of Transportation and Infrastructure to Construct the first phase of the 1.4 Billion...