Brookswood Firehall

Brookswood Firehall

Project Name: Brookswood Firehall Project Location: Langley Client: Township of Langley Duration: 3 months Scope: Replacing existing firehall with a new post-disaster, satellite firehall. Works inclusive of bulk excavation, ESC system (phase 1), and disposal. Clearing...
Perla and Onyx

Perla and Onyx

Project Name: Perla and Onyx Project Location: Surrey Client:  Polygon Construction Management Ltd. Duration: 5 months Scope: Off-site Roadworks and Site Servicing, including; storm and sanitary sewers, water works, street and pedestrian lighting, all civil works for...
Smith Brothers

Smith Brothers

Project Name: Smith Brothers Project Location: Langley Client: WrightSBW Duration: 4 months Scope: Early works for Smith Athletic Park – Youth Soccer Complex located in Langley. Phase 1 of this project will include site preparation works, site utilities including a...
Colebrook Dyke Ph.2

Colebrook Dyke Ph.2

Project Name: Colebrook Dyke Ph.2 Project Location: Surrey Client:  City of Surrey Duration: Phase 1 – 4 months Phase 2 – 3 months Scope: Phase 1. Approx 500 LM of improvements to the existing earth dyke at Mud Bay. Clearing and grubbing, approx. 28,000 m3 dyke fill....
Fraser Mills Phase 1B

Fraser Mills Phase 1B

Fraser Mills Phase 1B awarded to Tybo, scope of work included road works and installation of offsite service connections for storm sewer, sanitary sewer and forcemain, pump station, watermain, street lighting, pavement marking, traffic signals and signage, ESC,...