Colebrook Dyke Ph.2

Project Name: Colebrook Dyke Ph.2
Project Location: Surrey
Client:  City of Surrey
Duration: Phase 1 – 4 months Phase 2 – 3 months
Scope: Phase 1. Approx 500 LM of improvements to the existing earth dyke at Mud Bay. Clearing and grubbing, approx. 28,000 m3 dyke fill. Protecting wetlands and working within a popular park area while maintaining access.
Phase 2. Upgrades to approx. 200m along the northern shoreline of Mud Bay to meet near-term flood protection requirements using a nature-based design.