Project Name: Cariboo overpass

Project Location: Burnaby, BC

Client: Transportation Investment Corp

Duration: 1 year

Value: 9 million

Scope: Excavation and shoring, MSE retaining walls, road works, and bridge construction

Project Description: The project consist of replacement of the existing 2 lane Cariboo overpass with a new 4 lane structure complete with MSE walls, concrete abutments and both concrete and steel girders. In addition, a new off ramp will be constructed that will allow commuters to access Gaglardi way off of Highway #1, reducing congestion on adjacent routes and shaving valuable time off people’s daily commute.

Awards: Tybo Earns Nomination for contractor of the year award, read more at Journal of Commerce. What Langley MLA Mary Polak say about Tybo? Furthermore, Tybo is on the front page of Journal of Commerce spring issue of April 18, 2016 for earning the nomination for contractor of the year award click here to see the front page.